Scheme :: Parvati Giri Mega Lift Irrigation 

Introduction to the scheme

The programme has been launched by Govt. of Odisha during 2011-12 for providing irrigation to the farmers in the upland areas by lifting water from river, which could not be irrigated by normal means of flow irrigation. 

It is proposed to take up 174no mega lift schemes covering command area of 2,14,270ha. and grouped into 15 clusters as per the pre-feasibility study done during 2011.The first phase has been taken up in 2012-13 and the scheme is likely to be completed in a period of 3 years ending in 2015.Now DPR for 8 clusters have been prepared which contains 102 schemes against 96 schemes in PFR.

Site selection priorities

  • Projects having irrigation command area 500-2000 ha are taken up under the scheme.  
  • The scheme proposed to be taken up in 23 districts, which lie in the following river basins ie. Vansadhara, Indravati, Tel, Mahanadi, Brahmani, Baitarani and Burhabalanga of Odisha.  
  • Besides, some schemes have been identified in the periphery of Hirakud and Rengali reservoirs.
  • These schemes have been grouped into 15 clusters to facilitate tendering, execution and power connectivity point of view.
 

Funding arrangement

  • The scheme is being funded by the State Government.

Institutional arrangement

  • Minor Irrigation Organisation in the Minor (Flow) sector

    For smooth implementation of Mega Lift Project, a Project Management Unit (PMU) s created under the Deptt. of Water Resources. The Chief Engineer, Minor Irrigation, Odisha is declared as Project Director-cum-Chief engineer, PMU.

Project components

  • Detail survey and design.

  • Civil works like intake system, pump house, delivery chamber, residential building, approach roads etc.

  • Procurement and installation of electro-mechanical systems like pump, motor, transformer, overhead crane and control panel etc. 

  • Power system connectivity along with switchyard.

  • Rising main delivery water from the pump house to the delivery chamber.

  • Distribution system including distribution main, minors consisting of pipe line network.

  • Operation and Maintenance.

go to ToP

Project Details

  
SlNo Cluster No.

No. of 
Schemes

Area (Ha.)

1 Cluster-I 8 7,655
2 Cluster-II 12 11,680
3 Cluster-III 14 15,900
4 Cluster-IV 9 12,900
5 Cluster-V 8 12,000
6 Cluster-VI 8 15,000
7 Cluster-VII 7 5,600
8 Cluster-VIII 13 15,740
9 Cluster-IX 13 15,705
10 Cluster-X 13 19,795
11 Cluster-XI 12 15,595
12 Cluster-XII 16 21,300
13 Cluster-XIII 12 10,200
14 Cluster-XIV 13 18,450
15 Cluster-XV 15 18,400
 

Total:

174

2,14,270
 

Cluster Map

go to ToP

Procurement status

  • The projects have been proposed to be executed through Engineering Procurement Contract (EPC) mode.

 

  • EPC contract for two clusters (i.e XIV & XV) in Tel river basin having 28 schemes amounting to Rs.646.56 crores covering 35450 Ha. in the districts of Kalahandi,Bolangir,Boudh and Subernapur have been awarded to M/s L&T,Chennai as detailed below. 

     
    District Ayacut Area  Nos. of  Scheme
    Kalahandi 7700 Ha. 7
    Bolangir 16850 Ha. 14
    Sonepur 3900 Ha. 3
    Boudh 7000Ha. 4
    Total 35450 Ha. 28

     

 

  • The schemes under Cluster -XIV &XV will be commissioned in two and half year (Date of commencement-06.08.2013 & stipulated date of completion-05.02.2016).

 

  • L&T has also been awarded contract for the operation & maintenance of the schemes for five years after completion.

Details of Ongoing & Completed  Mega Lift Projects(13 Nos. of Cluster)

SlNo Cluster No. No. Of Scheme Name of The River Name of The District Ayacut area in Ha. DPR       Cost in Cr. Agreement cost excluding O&M cost in Cr. Cumulative Expenditure as on 31.03.2018  Date of Commencement  Stipulated/Extended Date of completion Status                               
1 2 3 4 5 6 7 8 9 10 11 12
1 XIV 13 Tel & Ret Kalahandi & Bolangir 14300 295.47 256.96 244.72 06.08.2013 05.02.2016/ 05.02.2017(EOT submitted to DoWR for approval) Thirteen  schemes(Tundula-I-500,  Tundula-II-600ha, Laitara-500Ha., Utkela-1500Ha.,Gurujibhata-2000 ha,Amath-600 Ha,Dunguripali-1000ha, Belgaon-500Ha.,Palam-2000ha,Hatikhoja-2000ha,Siskela-900ha,Bhuskimal-1200ha & Kusmal-1000Ha. ) have been completed by M/S L & T Ltd.
2 XV 15 Raul & Tel Bolangir, Sonepur & Boudh 21150 445.49 374.02 357.63 06.08.2013 05.02.2016/  05.02.2017(EOT submitted  to DoWR for approval) Fifteen schemes (Tandigaon-2000ha.,Kapsila-900Ha.Tentulikhunti-1500ha.Gudvella-750Ha. ,Mahajanapara-800ha.,Amdhan-800ha.,Sesanpali-1500ha,Brahmanipal-2000ha,  Rekdol-2000ha.,Ainapali-1500ha,Tambasina-1500ha,Kantamal-1500ha,Gunjimunda-800ha Tikarapada-2000ha&pandkimal-1600ha) ) have been completed by M/s L & T Ltd.
3 III 19 Bheden, Mahanadi & ONG Bolangir, Baragarh, Jharsuguda & Sambalpur 24020 622.48 507.29 470.10 18.03.2015 17.09.2017(EOT submitted  to DoWR for approval) Fourteen schemes (Agalpur-1000Ha. , Bharsuja-500Ha.,Chikhili-2000ha,Jampali-1320ha, Tamdei-1400ha,Jamutpali-1200ha,Ktikula-800ha,Samasingha-1000ha., Sodamal-800ha,Kudabaga-500ha,Janakdihi-1300ha,Saida-2000ha, Chandinimal-1500ha&Budhalpali-1500ha) have been completed & other schemes are in progress by M/s L & T Ltd.
4 I 8 Vansadhara, Sannai & Sananadi Gajapati & Raygada 7655   217.00 161.99 24.09.2015 23.03.2018 Work in progress by M/s GVPR Engineers Pvt. Ltd.
5 II 13 Hati, Indravati, Kolab & T.Channel Kalahandi, Koraput, Malkangiri & Nawarangpur 10980 249.77 212.60 161.58 24.09.2015 23.09.2018 Two Schemes(Chadapur-500ha&Chhatabandugura-900ha)have been completed & other schemes are in progress byM/s. GVPR Engineers Pvt. Ltd.
6 VI 9 Mahanadi Cuttack 16750 430.64 378.00 299.65 21.12.2015 20.06.2018 Work in progress by M/s L & T Ltd.
7 VIII 13 Brahmani Angul, Deogarh & Sundargarh 16200 428.93 339.43 246.60 21.12.2015 20.06.2018
8 XI 12 Birupa, Dudhei, Kelua, Kharasrota, Kharsuan, Luna & Tantighai  Jajpur & Kendrapara 15595 379.02 320.58 247.89 21.12.2015 20.06.2018
9 VII 14 Badanadi,Bahuda, Padma & Rushikulya Ganjam 14255 449.86 399.95 181.90 26.12.2016 25.06.2019 Work in progress by M/s Megha Engineering &Infrastructure Ltd.
10 IX 12 Deo,Koel &Sankha Sundargarh 14805 461.17 428.19 130.79 26.12.2016 25.06.2019 Work in progress by M/s L & T Ltd.
11 X 13 Baitarani,Deo,  Burhabalanga,Gangahar, Naiua,Khadakhai &Katra Keonjhar&Mayurbhanj 19400 568.78 508.07 164.81 26.12.2016 25.06.2019 Work in progress by M/s GVPR Engineers Pvt. Ltd. &  L & T Ltd.
12 XII 16 Basundhara,IB Ichha &sapei Jharsuguda &sundergarh 21300 649.28 588.59 246.55 26.12.2016 25.06.2019 Work in progress by M/s L & T Ltd.
13 XIII 12 Indra,Jonk,Sunder, Tel &Udanti Kalahandi&Nuapada 10200 311.27 291.36 101.37 26.12.2016 25.06.2019 Work in progress by M/s GVPR Engineers Pvt. Ltd. &   L & T Ltd.
Total 169     206610 5292 4822.04 3015.58      

Operation & Maintenance (O&M) of the project

  • The operation and maintenance of the of the scheme will be done by the EPC contractor.

 go to ToP

Year-wise Budget provision and expenditure incurred upto March'2018  (Unit: Rs. in Cr)  
Fin. Year
Original Budget in Cr.
Revised Budget in Cr. Expr in Cr. % Expr
11-12 50 30 30 100
12-13 150 7.17 4.10 57.18
13-14 200 175 59.73 34.13
14-15 325 325 317.10 97.57
15-16 State Plan 270.00 319.02 318.78 99.92
RIDF 275 275 275 100
Sub-Total 545.00 594.02 593.78 99.96
16-17

 

State Plan 510.00 815.03 814.76 99.97
RIDF 150.00 201.40 201.40 100
Sub-Total 660.00 1016.43 1016.16 99.97
17-18

 

State Plan 1043.82 575.97 575.59 99.93
RIDF 300.00 823.13 823.13 100
Sub-Total 1343.82 1399.10 1398.72 99.97

 

 

Technical Details

Typical Layout Map

Typical Pipeline Section

Typical Pump House

Typical Switch Yard

Ayacut Area Of Ongoing Mega Lift Projects of Odisha

 

go to ToP